VLT® Drives heat up Copenhagen passing under the royal castle
2 August 2010
|
Copenhagen Energy’s district heating system provides 98% of the city with clean, reliable and affordable heating. This heating system uses heat from waste incineration plants and combined heat / power plants.
READ MORE >
VLT® Solutions Early in 2010 the main supply of heat was changed from two old coal fired power plants to the renovated Amager Power Station, a high efficiency coal and biomass power plant. The steam and water pipes run in a new tunnel under the harbour - connecting the power station to the city heating system. This project was the second largest and most challenging civil engineering project in the history of Copenhagen. Interestingly, the tunnel is placed right below Amalienborg – the home of the Danish royal family.
The new tunnel and pumping station are owned by Copenhagen Energy. Amager Power Station is owned by Vattenfall. The engineers from Vattenfall have designed the pumping station that moves the hot water and steam into the city – and brings the return water and condensate back to the power station.
Reliability and energy efficiency Key criteria in the design phase were reliability and high energy efficiency. The system was commissioned in October 2009 and in full operation in December 2010, ready for a long and cold winter.
Saves 200,000 t of CO2 a year The total cost for the project, in excess of € 100 m, will be paid back by the annual savings in energy and operational costs after approx. 15 years. The citizens of Copenhagen receive clean, reliable heating at no extra cost and save 200,000 t of CO2 every year.
VLT® AQUA Drive There are 6 x 355 kW pumps for the forward and return flow of heating water and 3 x 160 kW pumps to pump the water from the power station through the heat exchangers. 4 x 37 kW pumps are used to bring the steam condensate back.
All pumps are speed controlled by Danfoss VLT® AQUA Drive FC 202. “We selected Danfoss because they offered the right product solution and the best value proposition” says Michael Skou Behrndtz, MSB Electrical Engineering, who designed the electrical system for the pumping building. “We expended a lot of effort to prevent problems with EMC and harmonic distortion as we know it is easier to do it right first time than to try to solve problems afterwards.”
Running on one transformer He designed the pump house with 2 x 10kV/400V transformers which normally run in parallel, but the system will keep running on one transformer in the event of a failure.
Built-in DC link chokes to keep the harmonic distortion down The built-in DC link chokes of the Danfoss drives are sufficient to keep the harmonic voltage distortion below the site standard. There are provisions to add an active harmonics filter if the heating capacity is increased and more speed controlled pumps are added.
Guaranteed availability of spare parts and qualified service All the Danfoss drives in this project are covered by a service agreement with guaranteed availability of spare parts and qualified service engineers on standby 24/7/365.
For further information contact:
Danfoss Ltd Capswood Oxford Road Denham Buckinghamshire UB9 4LH
Tel: 0870 241 7030 Fax: 0870 241 7035 Email: uk.controls.sales@danfoss.com Web: www.danfoss.co.uk
|
|