New, large scale biomass plant opts for energy efficiency

15 August 2012

More than forty Danfoss VLT® frequency converters are used in a new Dutch biomass plant’s sophisticated process control systems. Chosen for their high efficiency in large scale operations, the drives also support the plant’s green ambitions. In a field that is developing quickly, anaerobic digestion is currently looking like an attractive proposition in sustainable energy production. Not only does it provide a solution for the treatment of all sorts of biodegradable waste; it also produces a constant supply of energy in the form of gas, which can be converted to electricity. The waste products are clean water and organic fertiliser, which can be completely reused.

One of the largest digestion plants is the Lijnco Green Energy Biomass Plant (LGE), part of Biopark Terneuzen, which is to receive investments of EUR 0.5 billion. The biomass plant is one of the biggest sustainable energy projects in the Netherlands and will cost more than EUR 35.5 million and will produce gas which is then used to generate clean electricity. The only subsidy available for this is the Sustainable Energy Stimulus Scheme (stimuleringsregeling voor duurzame energie, SDE+).

Output constantly rising
The project is being implemented by the Schücking Energy Group from Enschede and Lijnco from Groningen and is managed by process technologist Jupp Schücking.

The technology for the biomass plant is being provided by HME
Engineering for the industrial automation and process control systems; and Mosch Thermische Installaties (MTI) for the mechanical systems.

The Schücking Energy Group has already completed a number of biogas plants in the Netherlands and other countries, including the world’s first mono-digester for animal waste. A key characteristic of their projects is the large scale. “Numerous small-scale facilities are already in use in the Netherlands.

Unfortunately, their capacity is much too small. You need at least 1 megawatt to make it worthwhile. We build large plants rated at 1 megawatt and above. In total, we have now installed around 50 megawatts of capacity. In four years time, we will have doubled this. In Europe, we rank among the largest builders of biomass plants”, explain Jupp Schücking.

The LGE Biogas Plant currently processes more than 300 tonnes of biomass per day, with a capacity of 135,000 tonnes per year. At the moment the plant is increasing its production to 6,000 cubic metres of gas per hour and 5 megawatts of energy. “This should increase to 10 megawatts by the end of 2011, and we expect the output to double again sometime in the future. The electricity is sold to energy supplier Delta N.V.,” says Jupp Schücking.

Scale is crucial for optimum results
Scale is extremely important in biomass plants because the fermentation process requires constant monitoring. Fermentation involves a large number of bacteria that live in a delicate balance with the various organic substances. The rate at which organic substances are digested varies considerably.

For instance, wheat is digested in 40 days, while glycerine takes only 24 hours. Maize, by contrast, takes a full 80 days. This biological process must be constantly fed, just like farm animals. If there is too little input, the digestion process will stop, and if you overfeed, the mass will start to froth and overflow. Production downtime is highly undesirable, because it can easily take eight days of extra effort to get the process going again.

Anaerobic digestion is therefore not something that farmers can do on the side. The process requires specially trained staff to manage the processes, and this is only possible if the scale is right.

Ambition to set new standards
“We want this plant to set the standard and be a model that we can reuse in subsequent projects. We drafted the functional requirements for the electrical system. Important elements in this are the forty or so Danfoss VLT® frequency converters, including a large number of 45 kW drives. These are used, for instance, to drive the many pumps and mixers that are essential in keeping the fermentation process going. There are ten 22 kW and 30 kW Seepex pumps between the large tanks,” says Heino Oltwater of HME Engineering, who continues “This is the first time that I have used Danfoss frequency converters. Van Egmond Elektrogroothandel in Doetinchem recommended the Danfoss VLT® frequency converters because they have 2% higher efficiency. They therefore contribute to the clean credentials of the plant. This also applies to the high-efficiency electric motors used in the drives.”

The frequency converters were supplied by Van Egmond, a company that HME Engin has done business with for a long time. They are a Danfoss distribution partner and can supply all frequency converters from stock, allowing the entire construction process to proceed smoothly.

Furthermore, Van Egmond Industrial Automation built the accompanying panels and developed the control and visualisation software for the plant.

Drives in Lijnco Green Energy Biomass Plant
A wide range of VLT® AutomationDrives, from 1-45kW help control the many intricate processes that lead to clean energy, supported by networking and safety options.

2x FC302 1 kW
1x FC302 1.5 kW
5x FC302 3 kW
7x FC302 4 kW
4x FC302 5 kW
3x FC302 11 kW
1x FC302 15 kW
5x FC302 22 kW
3x FC302 30 kW
2x FC302 37 kW
6x FC302 45 kW
11x Profibus modules
10x LCP2 graphical displays
10x MCB 108 Safety PLC IF

Basics of biomass production
The biomass plant digests waste according to the co-digestion principle. Co-digestion means that agricultural and food wastes are digested together with animal manures. The waste comes from companies that process grain, maize, sunflower seeds and soy beans to make foods and animal feeds. This results in organic waste matter such as animal skins, which are generally unusable apart from anaerobic digestion. These materials are mixed with glycerine and animal manure, which is supplied from across the entire country.

Digestion takes place in seven tanks with a total volume of 35,000 cubic metres. The biogas produced is collected in a secondary digester which is recognisable by its bulging tarpaulin cover. Below this is the methane gas, which must be compressed and dried before it is ready for combustion in the gas turbines. The remaining biomass is purified using a membrane filtration and drying system.
What remains is clean water and organic fertiliser. The fertiliser contains nitrogen, phosphates and potash, which can readily be sold to the agricultural industry as organic, non artificial fertiliser, which is a scarce substance which production usually involves high levels of CO2 emissions.

From an environmental perspective being able to reclaim them is very important. The biogas plant has its own water purification facility that can produce as much clean water as a sewage treatment plant for 1.5 million people. In total, the biogas plant represents a reduction in CO2, methane and nitrogen emissions by around 23,000 tonnes per year.

Biopark Terneuzen: total investment EUR 500 million

Lijnco Green Energy Biomass Plant: capacity 135,000 tonnes of waste from the food industry and agriculture

For further information, please contact Sara Bernard:

Danfoss VLT Drives

Capswood
Oxford Road
Denham
Buckinghamshire
UB9 4LH

Tel: +44 (0)1270 757584
Fax: +44 (0)1895 617149
Email: sara.bernard@danfoss.com 
Web: www.danfoss.co.uk/vlt
PandCT.com are not responsible for the content of submitted or externally produced articles and images.
Click here to email PandCT about any errors or omissions contained within this article.
     
Send this page
To send this page to a colleague or friend,
fill in the email addresses below...
Your email address
Their email address:
Page to be sent: shownews.asp?ID=33862

Company gateway pages
for Danfoss VLT Drives:
FREE Information on the products in this article
To request more information from this supplier,
fill in your email address below.
Your email address
 
     
Bookmark and Share
Product categories: Accelerometers | Actuators | Agitators | Analysers | Bearings | Compressors | Controllers | Conveyors | Drives | Enclosures | Flowmeters | Heat Exchangers | Motors | Pumps | Relays | Sensors | Transducers | Transmitters | Valves | Weighing
(c) Copyright 1999-2018 Process and Control Today Ltd  |  Reg. no 3733110  |  Email Editor  |  Email Webmaster  |  Sitemap  |  Privacy Policy