In focus manufacturing

The leading and longest established online Process Engineering publication serving the Process Manufacturing Industries

EXSEL PUMPS THE DOCK DRY WITH RALSPEED

Faced with the requirement to pump three million litres of water from Liverpool's Langton Dock in just three hours, Exsel Pumps decided to rely on variable speed drive systems from Ralspeed to control the pumps it would use for this challenging project.

Currently, £10 million is being invested in upgrading lock gate facilities at the Port of Liverpool, one of the largest and busiest container ports in Europe.

It would be too costly and disruptive to take the lock out of service for the whole duration of the project, which will take around three years. The decision was therefore taken to refurbish the caissons one at a time, which would allow the lock to continue to function while the work was being carried out, albeit with reduced flexibility.

To achieve the changeover of the caissons it was necessary to pump out and refill the caissons recess, which holds three million litres of water, several times. And, in order to limit the amount of time for which the lock was out of service, and to cater for variations in the tides around the dock, the time available for each of the emptying and filling operations was to be completed in less than three hours.

Exsel Pumps offered four 200 kW pumps, two of which were configured for emptying the dock, the other two for filling it. As the electricity supply was generator fed, the use of a variable speed drive enabled a reduction in generator size and a reduction in fuel consumption.

As the drives would be used outdoors, they needed to be weatherproof and be capable of resisting the effects of almost continuous exposure to seawater and salt spray. Further, since the caisson exchange was taking place in the middle of winter, the drives had to able to operate reliably at low temperatures.

Since Exsel Pumps required the drives only for the duration of the project, it decided that it would be more cost effective to hire them rather than buy them.

For this project, Ralspeed supplied two custom-built drive systems, each comprising a 200 kW Vacon NX drive and ancillary components mounted in a rugged weatherproof enclosure. Since filling and emptying operations would never be carried out simultaneously, rather than providing four separate drives Ralspeed supplied a changeover switching system that would allow the drives to be switched almost instantly to work with either the filling or the emptying pumps. This arrangement provided a very cost-effective solution.

For further information, please contact:

Debby Rooney, Ralspeed Ltd
A1 Hurstwood Court, Mercer Way, Shadsworh Business Park, Blackburn, BB1 2QU Tel: 01254 582345 Email: debby@ralspeed.com Web: www.ralspeed.com

Request FREE information from the supplier on the products in this article

Login or Register

Process and Control Today are not responsible for the content of submitted or externally produced articles and images. Click here to email us about any errors or omissions contained within this article.

Get the weekly eNewsletter from Process and Control Today